Documents for the Atmospheric Chemistry Lab Renovation Project
Background Documentation
Pictures of the lab space before renovation
Pictures of RF testing in Cristol tower for roof-mounted cell phone tower interference (11/20/2011)
Lab photos from David Oonk, NE corner
Lab photos from David Oonk, NW corner
Specifications for the Lab
General Lab Specifications
General Lab Specs (final version v1.6, shared w/ design team on 11-Feb-2012)
General Lab Specs (intermediate version v1.5, shared w/ design team on 12-Dec-2011)
(w/ track changes)
General Lab Specs (initial version v1.2, shared w/ design team on 20-Jun-2011)
Minutes from the 1st meeting of the design process, which record the importance of the temperature and other specifications
Chamber Light Specifications
Specifications for chamber lights (version 1.2, shared w/ design team on 7-May-2012)
Revised light specifications (v 1.3 of 12-Sep-12):
Clean PDF
and
Track Changes version
Efficiency of Fluorescent Bulbs vs. Temperature (from Phillips Catalogues)
UV Blacklights
Visible lights (both T5/T8s)
List of equipment to be purchased by scientists
(and installed after end of construction)
Preliminary allocation of offices
CFD Modelling of the Temperature Distribution in the Chamber
(Provided by RMH in Sep 2012)
Calculations of Transition Times in Chamber
(Provided by RMH in Oct 2012)
100% DD Submission (dated 16-May-2012)
List of comments w/ editable responses
ARCH drawings w/ comments
MEP drawings w/ comments
50% CD Submission (dated 16-July-2012)
Architectural Drawings
MEP Drawings
Proposed finishes and options
List of Comments w/ editable responses
100% CD Submission (dated 4-Oct-2012)
Architectural Drawings
Specifications (Vol. I)
Specifications (Vol. II)
Revit Model (Architectural)
Revit Model (MEP)
List of Comments w/ editable responses
Final 100% CD Submission (dated 21-Dec-2012)
Architectural and Engineering Drawings
Specifications (Vol. I)
Specifications (Vol. II)
Addendum 001a-d
List of Comments w/ editable responses
Additional Bid Documents
Addendum_003.pdf (dated 21-Feb-2013)
Rebid Final 100% CD Submission (dated 2-Jul-2013)
Schedule
(per Larry Hill's email of 13-June-2013)
Updated Schedule
(per Larry's email of 15-July-2013)
Architectural and Engineering Drawings
Specifications (Vol. I)
Specifications (Vol. II)
Supplemental Narratives
List of Comments w/ editable responses
Construction Phase
Summary of Bids
Scientist Punchlist Attention Items
Circuiting and Banking for Chamber Vis/UV Lights
Pure Air System Addendum, as submitted to JCor on Apr 29th, 2014
Specs of New Ballasts:
Part 1
&
Part 2
Commissioning Checklist and Status
Commissioning Plots and Notes
Commissioning Phase
RMH Report on Brown Chamber Testing (Aug/Sep 2015)
Responses from Scientists to RMH Report on Brown Chamber Testing
(21-Oct-2015)
Sequence of Controls with light power predictive loading protocol (RMH, Nov. 2015)